MONDAY 22nd


We had decieded to use our own Independent Inspector along with Porter Davis's one....just for peace of mind.
We had an appointment at 10.30 to meet our inspector out at the block.  When we got there Alex was waiting for us and to our surprise there were workmen on the block cutting the wood for the frame, now this really was a surprise as our SS had told us that work would commence on the Tuesday.
The inspection went really well, the only issue he had was that the slab had been pushed back into the block by 6cm...it really didn't faze us, Alex explained that all the pipes were for in the slab and how things should be done which we liked.....if you are complete novices it would really be piece of mind for you....but lucky for us we have been going on the Homeone forum for months and months reading all the stories so we were pretty much up to par on that account.
Alex promised to email the statement to us and told us to let him know when the roof trusses arrived so he could book us in for the next inspection.

That night we went back to the block to see what the men had done and to go walking on it....oh boy! does it look big and where we excited.....just a smidge...okay okay so i lied! we were excited heaps!! now are you happy?
the slab in the morning

and later that night...all ready to go